Hey, it has been a long time since I last posted here... I have been busy with work the last few months, though I still passed by the site several times and noted the progress.
I observed that it takes approximately 3 weeks to stack one storey in all the four blocks. This pace has been consistent since the stacking started, no stopping of work and no rushing of work seen.
<u>Blk 455</u>
This block is the slowest of all the four blocks. Currently, units 141 to 147 are near completion of the 6th storey with the final touches of its ceiling. Units 101 to 107 are slightly faster, with the completion of the flooring at the 7th storey.
<u>Blk 456</u>
This block is still at 8th storey, though it seems that they are more or less done with this storey.
<u>Blk 457</u>
Units 135 to 139 are at the start of the 9th storey. Units 129 to 133 are faster at the 10th storey.
<u>Blk 458</u>
This block is the highest of all at the 11th storey.