Hi Greenies
I went to visit BLK 489, I was rejected to access the block by an Indian Supervisor. From my visit there, only 490 seems to be completely done up.
Status of each block based on my observation.
487 - 75% completed and it seems like it will take another 1.5 months before it can be completed for inspection.
1) Windows Glass not installed
2) Window Grill (Hall) not installed
3) Painting not done.
488 - Completed, the lift was working, the are planting the grass patches.
489 - 95% Completed, Only one side of the building needs to be painted. Lift was already working (Presumed - Coz I see some workjers checking on the window grills at 12th Floor, I believe they would not possibly climb up)
490 - 85% Completed, Many areas required painting, not all window grills are fixed on.
I did managed to view the 489 kitchen and service yard area, thanks to my tele-lense, the access door was beautiful... pictures will be up shortly (Only 489)