SitRep as at 28th Feb 2010 1800hrs
633D progress is the fastest, encasing for the vertical column for ground level is up. Main steel beam for the Level 2 floor is up too. Next step probably pouring of concrete, should be able to see the vertical columns for level 2 within Mar
http://www.flickr.com/photos/91842697@N00/4394159437/in/photostream/
Next up, 633A , steel for vertical columns up. probably able to put up the floor of level 2 by end of Mar
http://www.flickr.com/photos/91842697@N00/4394997048/
633B flooring of ground level yet to be up
http://www.flickr.com/photos/91842697@N00/4394179433/in/set-72157623371597494/
633C is the slowest among the 4 blks. Pilings just started I think.
http://www.flickr.com/photos/91842697@N00/4394908634/in/set-72157623371597494/
MCSP yet to see the piling
http://www.flickr.com/photos/91842697@N00/4394171895/in/set-72157623371597494/
Rental blk seems to be as fast as 633D
http://www.flickr.com/photos/91842697@N00/4394894586/in/set-72157623371597494/
With the dry & hot spell of the El Nino expected to last until at least June, I guess they will not have much down time due to wet weather.